Brookleigh Eastern Bridge and Link Road: Isaacs Lane works under Traffic Management

John Sisk and Son is building the Eastern Bridge and Link Road, which will join Freeks Lane to Issacs Lane. They will be carrying out new internet network connections and highway improvement works along Isaac's Lane. These essential works are required to facilitate the construction of the new junction which will provide access to the Brookleigh development and relieve pressure on the existing road network by providing a through-road for Brookleigh traffic.

Before Sisk can start their junction works, Openreach will require a full road closure to complete internet network connections. This will take place every night between 20:00 and 05:00 from the evening of Monday 8th January through to the early morning of Friday 12th January 2024. A diversion route for vehicles will be clearly displayed with signage and businesses will be open as usual.

To undertake the works safely but also keep one lane open for traffic, it is necessary to install temporary traffic lights on Isaacs Lane from Monday 8th January through to 3rd June 2024.

Some of the work may require a full road closure. The proposed date under consideration to complete these works during night working hours of 20:00 to 05:00 is from Friday 31st May through to Monday 3rd June 2024. These works cannot be completed during regular working hours due to the impact on the road network. If the closure is required, notification will be given and a diversion route for vehicles will always be clearly displayed with signage and businesses will be open as usual.

All traffic lights will be manned within peak traffic periods to ensure and maintain the flow of traffic, an operative will be on site at all times to ensure that any unexpected flows are properly managed.

The network connection and highway improvement works form part of the Eastern Bridge and Link Road delivered in accordance with the associated planning consent DM/20/3247. Formal notice of the works has been submitted to and approved by Mid Sussex District Council.

We would like to apologise in advance for any inconvenience caused. If you have any questions about these works or concerns during the work period, please call John Sisk & Son Ltd on 01727875551 or message us or email This email address is being protected from spambots. You need JavaScript enabled to view it.

Mid Sussex District Council have opened applicatio...
We use cookies

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.